Overview

The theatre integrated into the Convention Hall complex at the north end of the boardwalk. Part of the Warren and Wetmore landmarks built 1928 to 1930. Closed, with repair obligations and the 2004 historic preservation easement on title: the Secretary of the Interior's Standards, and public access of at least twelve days a year, six hours a day, binding every future owner.

Public access

Closed, as confirmed November 14, 2026. The connecting Grand Arcade remains open.

Preservation obligations

Covered by NJSHPO preservation obligations as part of the Convention Hall / Paramount complex.

Grant and tax credit record

On August 20, 2026, the NJEDA Board approved up to $75,000,000 in CAFE tax credits for Convention Hall, the Paramount Theatre and the Grand Arcade, subject to conditions. MAR is the applicant; MAC holds title. This is a performance-based tax credit, not cash paid up front or confirmation of reopening.

Project cost / eligible costs
$150,015,586 / $128,115,586
Midloch Investment Partners bridge loan
$105,138,374
Boardwalk Preservation Fund
$13,000,000 subgrant to MAR from the City's $20,000,000 award; $7,000,000 retained for boardwalk and restroom work

The Board memo requires site plan approval. The pending $8,000,000 HPRP application must be complete by March 1, 2027, with approval within twelve months of CAFE approval; neither condition can be extended. If those conditions are not satisfied and HPRP credits are awarded, the CAFE award is reduced dollar for dollar. These figures overlap and should not be added as separate construction cash.

The separate Boardwalk subgrant funds Paramount exterior work. Its April 2026 Schedule A addendum records completion of Phase I investigations and design, sets Phase II at up to $11.7 million plus confirmed remaining Phase I funds, and states that grant funds terminate on December 31, 2026. It does not establish completion of the full Convention Hall rehabilitation or a reopening date.

What is unresolved

  • Reopening timeline
  • Programming responsibility
  • Final construction budget and satisfaction of CAFE / HPRP conditions

Key questions for officials

  • What is the current condition assessment on file?
  • What is the plan and schedule for reopening?