Where each building stands today

The historic buildings on the waterfront are in different conditions today, and the differences are worth stating building by building.

Convention Hall's ballroom has been closed since September 2021. The Paramount Theatre is also closed. The Grand Arcade connecting the two buildings remains open to the public as a walkway. These operating statuses were confirmed November 14, 2026.

At the Casino complex, the Arena, the section that faced the beach, was demolished in 2006. The Casino Arcade, the section spanning the boardwalk, has been closed since May 2023 due to deteriorating steel supports. The rest of the Casino building is closed. The Carousel section is open but has not been renovated. The Steam Plant next door is also closed.

The city has issued a series of formal default notices against the company responsible for these buildings. To be in default means the city has determined the company failed to meet obligations it agreed to. Resolution 2021-386, adopted in August 2021, cited failures to maintain the Convention Hall complex. Resolution 2023-89, adopted in January 2023, expanded those default notices to cover the Casino Building, the Steam Plant, and additional boardwalk structures. Resolution 2026-105, adopted in January 2026, authorized the city's outside counsel to issue updated default notices specific to the Casino Building.

The City received a $20 million Boardwalk Preservation Fund award and sub-granted $13 million to MAR for Paramount exterior work, retaining $7 million for boardwalk repairs and restrooms. The April 2026 Schedule A addendum records completion of Phase I investigations and design; it states that grant funds terminate December 31, 2026. Separately, on August 20, 2026, NJEDA approved up to $75 million in performance-based CAFE tax credits for Convention Hall, the Paramount Theatre and the Grand Arcade, subject to conditions. The Board memo presents a $150,015,586 project and a $105,138,374 Midloch Investment Partners bridge loan. The credits are not paid up front, and neither award establishes a reopening date.

What to watch

The Boardwalk grant term ending December 31, 2026; site plan approval; the March 1, 2027 HPRP completeness deadline and HPRP approval within twelve months of CAFE approval. Whether the City takes further enforcement action on the Casino complex.